The installation of the BiO2 Solutions technology at the city of Otterville is proceeding ahead of schedule.  The severe site limitations have presented some challenges.  The focus the past few weeks has been on completing the installation of the headworks (See pictures).  Upon completion of all the concrete work at the headworks, the concrete pads for the biological control center and the electrocoagulation (EC) buildings can then proceed.  The biological control center building is on site and the EC building is ready to transport to the city as soon as the concrete pads are completed.  The EC equipment is also ready to transport directly to the city for installation once the EC building is completed.

Further updates will follow in the upcoming weeks.  If you have any questions or would like to speak directly to a BiO2 representative, please contact us though the web site or call (303) 622-4567.